2021 ECO FUELS DANUBE GMBH

2021 ECO FUELS DANUBE GMBH

Location: Krems an der Donau, Austria

Project duration: 1 month

Scope: Assembly and pre-production of pipelines, and pipe distributions for doubling the production of BIO Diesel, Installation of pipe components and storage

Activity:

  • Transport of material
  • Prefabrication of pipelines on site
  • Installation of pipelines, pipe distributions and supports
  • Welding work
  • Preparation for sealing and pressure tests
2021 Synthesia, a.s.

2021 Synthesia, a.s.

Location: Pardubice, Czech Republic

Project duration: 3 weeks

Scope: Pre-production and installation of pipes in the heat exchanger/ connection of pipes between tanks

Activity:

  • Transport of material
  • Installation of the heat exchanger
  • Prefabrication of pipelines, subsequent assembly
  • Welding work
2021 TotalEnergies Raffinerie Mitteldeutschland

2021 TotalEnergies Raffinerie Mitteldeutschland

Location: Leuna, Germany

Project duration: 1 month

Scope: Assembly and pre-production of pipelines, pipe distributions, Installation of pipe components and storage

Activity:

  • Prefabrication of pipelines on site
  • Installation of pipes according to the drawing documentation
  • Welding work – TIG welding method
  • Preparation, production and assembly of supports and pipe supports
2021 ALLFINE s.r.o.

2021 ALLFINE s.r.o.

Location:Slovak Republic – Agricultural biogas station Kamenica nad Cirochou

Project duration: 1 month

Scope: Installation of pipelines for the transport of biogas, connection of pipelines between tanks and drainage pipelines, installation of supports

Activity:

  • Installation of DN150 pipes, connection of pipes between tanks and drainage pipes
  • Installation of supports
  • Planning
2020/2021 MiRO Mineraloelraffinerie Oberrhein GmbH & Co. KG

2020 MiRO Mineraloelraffinerie Oberrhein GmbH & Co. KGí

Location: Germany – Karlsruhe

Project duration: 8 months

Scope:

  • Assembly and pre-production of pipelines, pipe distributions
  • Installation of pipe components and storage

    Activity:

  • Prefabrication of pipelines on site
  • Installation of pipes according to the drawing documentation
  • Welding work
2020 Bučina DDD, spol. s r.o

2020 Bučina DDD, spol. s.r.o

Location: Slovak Republic – Zvolen

Project duration: 5 months

Scope: Installation of technological equipment for transporting wood chips

Activity:

  • Assembling a steel structure
  • Installation of technological equipment (Conveyors,screws)
  • Installation of hydraulics
2020 Slovnaft, a.s.

2020 Refinery Slovnaft, a.s.

Project duration: 5 months

Scope: Assembly and pre-production of pipelines, pipe distributions, supports and storage

Activity:

  • Prefabrication of pipelines on site
  • Installation of pipelines, pipe distributions according to drawing documentation
  • Welding work – TIG welding method
  • Preparation, production and assembly of supports and pipe supports
2019 FALCO Zrt.

2019 FALCO Zrt.

Location: Hungary – Szombathely

Project duration: 3 months

Scope: assembly of conveyors for transporting wood chips (conveyor length 80 m)

Activity:

  • Assembly of steel structure
  • Assembly of technological equipment (conveyors)
2019 KRONOSPAN CR, spol. s r.o.

2019 KRONOSPAN CR, spol. s.r.o

Place: Czech Republic – Jihlava

Project duration: 6 months

Scope: Installation of a boiler for heating thermal oil 12M, Installation of pipeline routes

Activity:

  • Assembling a steel structure
  • Assembly of technological devices
  • Piping works according to the drawing documentation
  • Welding work