2021 ECO FUELS DANUBE GMBH
Location: Krems an der Donau, Austria
Project duration: 1 month
Scope: Assembly and pre-production of pipelines, and pipe distributions for doubling the production of BIO Diesel, Installation of pipe components and storage
Activity:
- Transport of material
- Prefabrication of pipelines on site
- Installation of pipelines, pipe distributions and supports
- Welding work
- Preparation for sealing and pressure tests
2021 Synthesia, a.s.
Location: Pardubice, Czech Republic
Project duration: 3 weeks
Scope: Pre-production and installation of pipes in the heat exchanger/ connection of pipes between tanks
Activity:
- Transport of material
- Installation of the heat exchanger
- Prefabrication of pipelines, subsequent assembly
- Welding work
2021 TotalEnergies Raffinerie Mitteldeutschland
Location: Leuna, Germany
Project duration: 1 month
Scope: Assembly and pre-production of pipelines, pipe distributions, Installation of pipe components and storage
Activity:
- Prefabrication of pipelines on site
- Installation of pipes according to the drawing documentation
- Welding work – TIG welding method
- Preparation, production and assembly of supports and pipe supports
2021 ALLFINE s.r.o.
Location:Slovak Republic – Agricultural biogas station Kamenica nad Cirochou
Project duration: 1 month
Scope: Installation of pipelines for the transport of biogas, connection of pipelines between tanks and drainage pipelines, installation of supports
Activity:
- Installation of DN150 pipes, connection of pipes between tanks and drainage pipes
- Installation of supports
- Planning
2020 MiRO Mineraloelraffinerie Oberrhein GmbH & Co. KGí
Location: Germany – Karlsruhe
Project duration: 8 months
Scope:
- Assembly and pre-production of pipelines, pipe distributions
- Installation of pipe components and storage
Activity:
- Prefabrication of pipelines on site
- Installation of pipes according to the drawing documentation
- Welding work
2020 Refinery Slovnaft, a.s.
Project duration: 5 months
Scope: Assembly and pre-production of pipelines, pipe distributions, supports and storage
Activity:
- Prefabrication of pipelines on site
- Installation of pipelines, pipe distributions according to drawing documentation
- Welding work – TIG welding method
- Preparation, production and assembly of supports and pipe supports
2019 KRONOSPAN CR, spol. s.r.o
Place: Czech Republic – Jihlava
Project duration: 6 months
Scope: Installation of a boiler for heating thermal oil 12M, Installation of pipeline routes
Activity:
- Assembling a steel structure
- Assembly of technological devices
- Piping works according to the drawing documentation
- Welding work